Establishment of Lotus Pharma Project in Millawa
Environmental Recommendation from Central Environment Authority
Central Environment Authority Inspection Visit - 02.12.2021
- Obtained Environmental Recommendation from Central Environment Authority for Orthopedic and Neurological Implants, Oncology drugs, and Oral Solid Dosage forms (General Drugs) manufacturing plants separately.
Land Acquiring Process with UDA (Urban Development Authority)
The signing of the Lease Agreement between SPMC & UDA - 12.01.2022
- The 99 years lease agreement was signed between SPMC and UDA to obtain 65-acre land in Horana Millewa to establish SPMC Lotus Pharma Project
Selection of Independent Consultant for SPMC Lotus Pharma Project
The signing of the Contract for Consultancy Services agreement with M/s Meridian Engineering & Consultancy Services - 06.07.2022
- The cabinet approval was obtained for the employment of Meridian Engineers and Consultancy Services of India as the independent consultant for the SPMC Lotus Pharma Project SPMC signed the Contract for Consultancy Services agreement with M/s Meridian Engineering & Consultancy Services on 06th July 2022
Land Surveying Activities SPMC Lotus Pharma Project
- Land Surveying Activities of SPMC Lotus Pharma Project was carried out by Global GIS Pvt ltd on 07.10.2022 prior to the preparation of Site Master Plans for the Orthopedic and Neurological Implants, Oncology drugs, and Oral Solid Dosage forms (General Drugs) manufacturing plants separately.
Preparation of Site Master Plans for SPMC Lotus Pharma Project
- As per the instructions given by the Meridian Engineers and Consultancy Services (Independent consultant of SPMC Lotus Pharma Project), preparation of Site Master Plans was underway on 21.10.2022 by installing land marks in 03 block out sites and access road.